Carbon Steel Pipeline Replacement Without Welding at Pertamina EP

October 7, 2026
How our team replaced a carbon steel line in an extremely limited-access area at Pertamina EP, without welding or hot work.

What do you do when a carbon steel pipeline replacement has to happen in a space too tight for a welding crew? At Pertamina EP, we answered that question without lighting a single torch.

PT Saka Nusa Persada completed a carbon steel pipeline replacement at Pertamina EP Zona 14 Klamono, in an area with extremely limited access. Instead of welding, our team used LOKRING® cold connection technology. As a result, the work finished safely, quickly and without hot work.

Carbon steel pipeline replacement with LOKRING fittings at Pertamina EP
LOKRING installation in a limited-access area at Pertamina EP.

Project Background

The scope required removing and installing carbon steel piping where working space was severely restricted. Normally, welding needs room for equipment, worker movement and safety clearance. However, this site offered very little of each.

  • Extremely narrow working areas
  • Limited access for welding machines and heavy equipment
  • Restricted worker mobility
  • Higher safety risk from any hot work

The Challenge of Welding in Confined Spaces

Welding in a confined space brings limited ventilation, fire hazards and complex permits. Consequently, a conventional approach would have slowed the job and increased risk for everyone on site.

The Solution: LOKRING Cold Connection for Carbon Steel Pipeline Replacement

We installed LOKRING coldweld pipe fittings, a mechanical cold connection qualified to ASME B31 piping codes. Because the fittings join pipe without heat, they suit places where welding is impractical or unsafe.

  • No welding or hot work, so no fire watch or hot-work permit was needed.
  • Faster installation than welding, because there is no cooling or NDT step.
  • Lower risk in a hazardous, crowded environment.
  • Leak-tight, high-strength joints that meet ASME B31 requirements.

Faster Than Conventional Welding

A welded joint normally passes through surface preparation, welding, cooling, NDT and inspection. In contrast, a LOKRING joint is visually inspected right after installation. Therefore, the crew completed each connection in minutes and kept downtime to a minimum.

Safer Without Hot Work

Welding in narrow spaces raises the risk of fire, gas ignition, poor air circulation and fatigue. By removing welding altogether, the cold connection protected the crew while keeping pipeline integrity intact.

Results of the Carbon Steel Pipeline Replacement

The project showed how the right technology can overcome confined working areas and limited access. In short, Pertamina EP received a reliable, code-qualified connection, delivered faster and more safely than welding. You can learn more about the technology from LOKRING Technology, or see our LOKRING installation services.

Facing a similar replacement in a tight space? Request a technical assessment, and then we will plan a no-weld carbon steel pipeline replacement for your site.

Have a similar challenge?

Ask Our Engineers

Share your line, service and constraint. We will recommend a proven technology and the right principal.

Request a Quote

Let’s work together

Let’s talk about your next scope

Tell us the line, the service and the constraint, whether it is a shutdown window, access or budget. Then we will come back with the right technology, correctly sized, from the right principal.

Technical consultationProduct selection and sizing for your service conditions.
Proposal & documentationQuotation, datasheets and certificates for your procurement process.
Delivery & site supportLogistics to site, application support and after-sales follow-up.